We are continuing with ongoing work throughout the facility and below is the latest update on how we are progressing.
Changing Rooms – Repairs have been ongoing this week and will be completed by Friday 6th September.
Gym Equipment – There are still two pieces of equipment to arrive, a dual pec fly and back fly machine, also hip abductor/adductor. These are due in the next few weeks and an update will follow.
Squash Courts – Courts 2-6 will reopen by the end of this week. More updates to follow.
Studio 1 – Work progressing well, estimated time of opening Monday 9th September.
Sports hall 2 – Unfortunately due to unforeseen circumstances there has been a delay in the opening of the sports hall and the new estimated time of opening is Friday 6th September.
Free Weights – We are still working on a resolution for this area and are liaising with the insurance company at present. More details to follow.
If you have any questions in regards to the above areas, please contact hello@oriam.hw.ac.uk and we will be happy to assist.